LocationShanggao, Yichun, Jiangxi
Line level500kV
Recorded scope30.863 km / 72 towers
Recorded timingCompleted, Oct 2025
Project context.
This public project record covers the 500kV outgoing works from Shanggao Power Plant in Shanggao County, Yichun, including the Yichun–Jinjiang line and its connection at Jinjiang 500kV substation.